Reliability Coordinator – Actively Monitored Standards

Below is a summary of NERC standards being actively monitored for a Reliability Coordinator (RC). Currently, the Electric Reliability Council of Texas (ERCOT) is the region’s sole RC.


This summary is being provided to you as a courtesy. Texas Reliability Entity, Inc. (Texas RE) recommends that you refer to the 2010 Compliance Monitoring and Enforcement Program Requirements (CMEP) Spreadsheet on the NERC Web site for the complete set of standards and requirements that are actively monitored. To find the spreadsheet, go to Compliance, then Resources. Select Resource Documents External Link on the left navigation bar. From the list, select 2010 Actively Monitored Reliability Standards.

To find the NERC Reliability Standards, visit Reliability Standards External Link on the NERC site.

To find the Texas RE implementation plan for its NERC CMEP program, please visit the Compliance page.

Key:

Compliance Audit

Self-Certification

Planned Spot Check

Exception Reporting

Requirement

Resource and Demand Balancing
BAL-004-0
Time Error Correction R1., R2., R4.
Top of Page

Critical Infrastructure Protection
CIP-001-1
Sabotage Reporting R1., R2., R3., R4.
CIP-002-1
Critical Cyber Asset Identification R1., R1.1., R1.2., R1.2.1., R1.2.2., R1.2.3., R1.2.4., R1.2.5., R1.2.6., R1.2.7., R2., R3., R3.1., R3.2., R3.3., R4.
See Implementation Table
CIP-003-1
Security Management Controls R1., R1.1., R1.2., R1.3., R2., R2.1., R2.2., R2.3., R3., R3.1., R3.2., R3.3., R4., R4.1., R4.2., R4.3., R5., R5.1., R5.1.1., R5.1.2., R5.2., R5.3., R6.
See Implementation Table
CIP-004-1
Personnel & Training R1., R2., R2.1., R2.2., R2.2.1., R2.2.2., R2.2.3., R2.2.4., R2.3., R3., R3.1., R3.2., R3.3., R4., R4.1., R4.2.
See Implementation Table
CIP-005-1
Electronic Security Perimeter(s) R1., R1.1., R1.2., R1.3., R1.4., R1.5., R1.6., R2., R2.1., R2.2., R2.3., R2.4., R2.5., R2.5.1., R2.5.2., R2.5.3., R2.5.4., R2.6., R3., R3.1., R3.2., R4., R4.1., R4.2., R4.3., R4.4., R4.5., R5., R5.1., R5.2., R5.3.
See Implementation Table
CIP-006-1
Physical Security of Critical Cyber Assets R1., R1.1., R1.2., R1.3., R1.4., R1.5., R1.6., R1.7., R1.8., R1.9., R2., R2.1., R2.2., R2.3., R2.4., R3., R3.1., R3.2., R4., R4.1., R4.2., R4.3., R5., R6., R6.1., R6.2., R6.3.
See Implementation Table
CIP-007-1
Systems Security Management R1., R1.1., R1.2., R1.3., R2., R2.1., R2.2., R2.3., R3., R3.1., R3.2., R4., R4.1., R4.2., R5., R5.1., R5.1.1., R5.1.2., R5.1.3., R5.2., R5.2.1., R5.2.2., R5.2.3., R5.3., R5.3.1., R5.3.2., R5.3.3., R6., R6.1., R6.2., R6.3., R6.4., R6.5., R7., R7.1., R7.2., R7.3., R8., R8.1., R8.2., R8.3., R8.4., R9.
See Implementation Table
CIP-008-1
Incident Reporting and Response Planning R1., R1.1., R1.2., R1.3., R1.4., R1.5., R1.6., R2.
See Implementation Table
CIP-009-1
Recovery Plans for Critical Cyber Assets R1., R1.1., R1.2., R2., R3., R4., R5.
See Implementation Table
Top of Page

Communications
COM-001-1.1
Telecommunications R1., R1.1., R1.2., R1.3., R1.4., R2., R3., R4., R5.
COM-002-2
Communications and Coordination R2.
Top of Page

Emergency Preparedness and Operations
EOP-002-2.1
Capacity and Energy Emergencies R1., R8., R9., R9.2., R9.3., R9.4.
EOP-004-1
Disturbance Reporting R2., R3., R3.1., R3.2., R3.3., R3.4.
EOP-006-1
Reliability Coordination - System Restoration R1., R2., R3., R4., R5., R6.
EOP-008-0
Plans for Loss of Control Center Functionality R1., R1.1., R1.2., R1.3., R1.4., R1.5., R1.6., R1.7., R1.8.
Top of Page

Facilities Design, Connections, and Maintenance
FAC-011-2
System Operating Limits Methodology for the Operations Horizon R1., R1.1., R1.2., R1.3., R2., R2.1., R2.2., R2.2.1., R2.2.2., R2.2.3., R2.3., R2.3.1., R2.3.2., R2.3.3., R2.4., R3., R3.1., R3.2., R3.3., R3.3.1., R3.4., R3.5., R3.6., R3.7., R4., R4.1., R4.2., R4.3., R5.
FAC-013-1
Establish and Communicate Transfer Capabilities R1., R2., R2.1.
FAC-014-2
Establish and Communicate System Operating Limits R1., R2., R5., R5.1., R5.1.1., R5.1.2., R5.1.3., R5.1.4.
Top of Page

Interchange Scheduling and Coordination
INT-004-2
Dynamic Interchange Transaction Modifications R1.
INT-010-1
Interchange Coordination Exemptions R2., R3.
Top of Page

Interconnection Reliability Operations and Coordination
IRO-001-1.1
Reliability Coordination - Responsibilities and Authorities R2., R3., R4., R5., R6., R7., R9.
IRO-002-1
Reliability Coordination - Facilities R1., R2., R3., R4., R5., R6., R7., R8., R9.
IRO-003-2
Reliability Coordination - Wide-Area View R1., R2.
IRO-004-1
Reliability Coordination - Operations Planning R1., R2., R3., R5., R6.
IRO-005-2
Reliability Coordination - Current-Day Operations R1., R1.1., R1.2., R1.3., R1.4., R1.5., R1.6., R1.7., R1.8., R1.9., R1.10., R2., R3., R4., R5., R6., R7., R8., R9., R10., R11., R12., R13., R14., R15., R16., R17.
IRO-006-4
Reliability Coordination - Transmission Loading Relief R1., R1.1., R1.2., R1.3., R2., R3., R4., R5.
IRO-014-1
Procedures, Processes, or Plans to Support Coordination Between Reliability Coordinators R1., R1.1., R1.1.1., R1.1.2., R1.1.3., R1.1.4., R1.1.5., R1.1.6., R2., R2.1., R2.2., R3., R3.1., R3.2., R4., R4.1., R4.2., R4.3.
IRO-015-1
Notifications and Information Exchange Between Reliability Coordinators R1., R1.1., R2., R2.1., R3.
IRO-016-1
Coordination of Real-time Activities Between Reliability Coordinators R1., R1.1., R1.2., R1.2.1., R1.2.2., R1.3., R2.
Top of Page

Nuclear
NUC-001-1
Nuclear Plant Interface Coordination R2., R3., R4., R4.1., R4.2., R4.3., R6., R8., R9., R9.1., R9.1.1., R9.1.2., R9.1.3., R9.1.4., R9.2., R9.2.1., R9.2.2., R9.2.3., R9.3., R9.3.1., R9.3.2., R9.3.3., R9.3.4., R9.3.5., R9.3.6., R9.3.7., R9.4., R9.4.1., R9.4.2., R9.4.3., R9.4.4., R9.4.5.
Top of Page

Personnel Performance, Training, and Qualifications
PER-003-0
Operating Personnel Credentials R1., R1.1., R1.2.
PER-004-1
Reliability Coordination - Staffing R1., R2., R3., R4., R5.
Top of Page

Transmission Operations
TOP-001-1
Reliability Responsibilities and Authorities R8.
TOP-003-0
Planned Outage Coordination R1.2., R1.3., R4.
TOP-005-1.1
Operational Reliability Information R1.1.
TOP-006-1
Monitoring System Conditions R2., R3., R4., R5., R7.
TOP-007-0
Reporting System Operating Limit (SOL) and Interconnection Reliability Operating Limit (IROL) Violations R4.